Hi,
How do i split an order base line so that item count can be splited to many shipunits?
Currently from EBS we create the order base. But it creates one orderbase line per PO line and/or shipment. Our customer receives ready to ship information as a packing list from the supplier. It has partial quantities being packed into multiple ship units of different capacities.
Our customer wants to split the quantity so that they can plan for transportation exactly as it is mentioned in the packing list.
Example :
OB line 1 : 100 Ea
Packing List :
Box 1 : 15 Ea
Box 2 : 18 Ea
Box 3 : 10 Ea
Remaining quantities are still not ready and it will be available later.
Can anyone let me know how do i create a single order release which will have all these ship units.
Thanks.
How do i split an order base line so that item count can be splited to many shipunits?
Currently from EBS we create the order base. But it creates one orderbase line per PO line and/or shipment. Our customer receives ready to ship information as a packing list from the supplier. It has partial quantities being packed into multiple ship units of different capacities.
Our customer wants to split the quantity so that they can plan for transportation exactly as it is mentioned in the packing list.
Example :
OB line 1 : 100 Ea
Packing List :
Box 1 : 15 Ea
Box 2 : 18 Ea
Box 3 : 10 Ea
Remaining quantities are still not ready and it will be available later.
Can anyone let me know how do i create a single order release which will have all these ship units.
Thanks.
Comment