    Hi,

    I am planning a shipment using two location of Australia and using Transport mode as Air.
    Shipment is planning but I am not able to do secure resource from action.

    But when I am using TL as Transport mode then shipment is planning as well as secure resource also happening for the shipment.

    can any one guide me if I am missing any constrain for Transport mode Air.

    (N.B. Rate Service is simulation)

    Thanks in advance.

  • #2
    Re: Secure Resources not started

    You need to add the mode in the worflow parameter PREPARE_TO_ARRANGE_TRANSPORT.
    Business process automation -> Power data -> event management -> Workflow parameters

    Comment


    • #3
      Re: Secure Resources not started

      Just to add to Anirban post, Modify workflow parameter where,

      WORKFLOW INFO ID = PREPARE_TO_ARRANGE_TRANSPORT
      PARAMETER = TENDER_MODES
      VALUE = TL (Change it to TL, AIR)
      Regards,
      Prashant Jain
      Oracle Transport Management 6 Certified Implementation Specialist

      If my post was helpful please click on the Thanks! button

      Comment


      • #4
        Re: Secure Resources not started

        Hi,
        On reaching to Business process automation -> Power data -> event management -> Workflow parameters path, their is no option like new, add,etc for adding another parameter

        Can anyone please help on this

        Comment


        • #5
          Re: Secure Resources not started

          You do not add new parameter, just modify the value for existing parameter and change it to your requirement. By adding in the above post means, changing the value to include additional transport mode.
          -------
          Thanks and Regards
          Anurag Saini
          MavenWire

          Comment


          • #6
            Re: Secure Resources not started

            Thanks a lot Anurag

            Comment


            • #7
              Re: Secure Resources not started

              Even if you add them in some way like direct insert, that won't be useful because no OTM out-of-box process will use it.
              Regards,
              Prashant Jain
              Oracle Transport Management 6 Certified Implementation Specialist

              If my post was helpful please click on the Thanks! button

              Comment


              • #8
                Hi All

                Was this issue resolved.

                My parameters are find but I am still not able to tender my AIR Shipments.

                Comment


                • #9
                  Hi Ayush,

                  Hope you have modified the above mentioned parameter in the same domain i.e., <your domain name>.PREPARE_TO_ARRANGE_TRANSPORT. Plus, also check if allow tender option is enabled on your service provider.