Dear Pals,
Below was the problem I am facing right now.
Once the shipment is planned why is that the first pick up location (first stop) is not the same as the final drop off location (final stop in the sequence.) ..If the shipment starts from Stop A (pick up) --> Stop B (drop off)--> Stop C (drop off)--> Then this should come back to Stop A finally..
Below are the steps, I followed:
1) Order Releases are planned into a shipment by running the Bulk Plan - Buy Shipment in OTM system.
2) Once the planned shipment is generated the final stop location is not the same as the starting pick up location.
Ideally it should come back to the same location from where it started ... But not happening. Can any one suggest something?
Thanks & Regards,
Lakshman
Below was the problem I am facing right now.
Once the shipment is planned why is that the first pick up location (first stop) is not the same as the final drop off location (final stop in the sequence.) ..If the shipment starts from Stop A (pick up) --> Stop B (drop off)--> Stop C (drop off)--> Then this should come back to Stop A finally..
Below are the steps, I followed:
1) Order Releases are planned into a shipment by running the Bulk Plan - Buy Shipment in OTM system.
2) Once the planned shipment is generated the final stop location is not the same as the starting pick up location.
Ideally it should come back to the same location from where it started ... But not happening. Can any one suggest something?
Thanks & Regards,
Lakshman
Comment