  • Multistop Action vs Bulkplan

    Hi Everyone,
    I want to achieve Multistop Action result through bulkplan while planning two Orders. But bulkplan is not producing single shipment as cost of the single shipment is higher than total cost of two shipments produced by bulkplan. I've tried tweaking multistop logic configuration as per below but still unable to create a single multistop shipments. Any suggestion would be great help.
    Logic Configuration :
    MULTISTOP COST SAVING CHECK TYPE : 3. Do not perform cost saving check.
    MULTISTOP CONSOLIDATION ALGORITHM TYPE: 3. Column Generation

    Order Releases:
    OR1-A-->B
    OR2-A-->C

    Multistop Action Shipment Cost of Single Shipment: 120$
    Bulkplan Shipment Cost :
    SH1-->OR1-->60$
    SH2-->OR2-->55$

    Rate Offerring, Rate Records remains the same.

    Thank You!
    GP